DIYSumsPaving slab calculator: slabs, MOT Type 1, sand and cement

A solid start for your next project

Paving slab calculator: slabs, MOT Type 1, sand and cement

Estimate the paving slabs, sub-base, bedding mortar and jointing compound for a UK patio, then turn the quantities into a shopping list.

Garden & outdoors Sources & assumptions

Your project worksheet

Let’s measure it up.

How will you enter the patio size?
20
Slab size or mix
100
The cited merchant guide suggests about 30 to 40 mm, use the depth for your chosen method.
40
1 : 4 by volume (sourced bedding mix)

Bedding mortar mix ratio (cement : sharp sand)

The default is 0%, change it to suit your layout and cutting plan.
0
10 mm

Joint width (mm)

Brush-in jointing compound, 15 kg tub (FPM example)

Jointing product

Your inputs stay in your browser.

Your result

Your plan starts
with a few details.

Enter the patio area and select Calculate. Your slab, sub-base, bedding and jointing shopping list will appear here.

For general information only, not professional advice. Rules and prices change, so check the official sources below. Use your own judgement and speak to a qualified professional before you act.

How it works

Enter the patio area directly or enter its length and width. Select one-size 600 x 600 mm or 600 x 900 mm paving, or the sourced four-size sandstone project pack. Add the compacted sub-base depth, mortar-bed depth, a waste allowance, and the joint width. The result rounds whole slabs, project packs, bags and tubs up so the list contains full items to buy.

MOT Type 1 estimates use one named UK merchant’s stated approximate coverage and its 850 kg bulk-bag mass. Sharp-sand and cement estimates use the published bedding-mortar table for the selected 1 : 4 mix. Jointing compound quantities use the maker’s coverage table for the selected slab pattern and joint dimensions. Local products, moisture, ground conditions, cuts and installation methods change actual quantities, so confirm the delivered products and follow their instructions.

Formula

  • Count individual slabs or project packs

    Order area = patio area × (1 + waste %) Slabs = ceil(order area ÷ ((slab length + joint) × (slab width + joint))) Project packs = ceil(order area ÷ pack coverage)

    Slab dimensions and pack coverage come from the selected product data.

  • Estimate the bedding mortar

    Bedding volume = patio area × bed depth Cement bags = ceil(volume × 8 bags per m³) Sharp sand = volume × 1,000 kg per m³

    These rates use the cited 1 : 4 cement-to-sharp-sand bedding mix. The calculator rounds quantities up to whole packs.

  • Estimate jointing compound and sub-base

    Joint tubs = ceil(order area ÷ maker coverage for your slab and joints) MOT bags = ceil(required volume ÷ merchant coverage at the chosen depth) Tonnes = whole MOT bags × 850 kg ÷ 1,000

    The MOT estimate uses the named merchant’s approximate coverage for its 850 kg bulk bag.

Worked example

  1. Estimate the slabs

    ceil(20 m² ÷ (0.61 m × 0.61 m)) = 54 slabs

    The example uses 600 mm slabs, 10 mm joints and no added waste.

  2. Estimate the sub-base

    ceil(20 m² ÷ 5 m² per bag) = 4 bulk bags

    At 850 kg each, the whole bags weigh about 3.4 tonnes in total.

  3. Estimate the mortar bed

    20 m² × 0.04 m = 0.8 m³ 7 cement bags · 800 kg sharp sand

    This uses a 40 mm bed and the cited 1 : 4 bedding mix. The sharp sand fits in one approximate 850 kg bulk bag.

  4. Estimate the jointing tubs

    Maker coverage for these slabs and joints → 2 × 15 kg tubs

    The selected FPM coverage table supplies the tub count, follow the maker’s joint-width and depth guidance.

  5. Compare the four-size project pack

    2 project packs for the same 20 m² patio

    Each pack contains 48 slabs across four sizes. This option is counted by the pack’s stated area coverage.

Assumptions and limits

The single-size slab estimate adds the chosen joint width to both slab dimensions to estimate the repeating covered area. A real patio layout may require cuts, perimeter trimming or a different starting pattern, add a waste allowance that reflects your layout. The project pack uses its merchant-stated pack coverage and fixed composition. It is one sourced sandstone product example, not a universal mix pack.

The MOT Type 1 source lists approx. 5 m² at 100 mm and an 850 kg bulk bag. It separately states approx. 2 tonnes per m³, that density claim conflicts with the coverage and bag-weight figures, which imply about 1.7 tonnes per m³. To keep this result internally consistent, the calculator uses the stated coverage to count whole bags and derives tonnes from those whole bags x 850 kg. Treat both outputs as approximate product-specific estimates and confirm them with your supplier.

Bedding quantities assume the cited 1 : 4 cement-to-sharp-sand bedding mix and its approximate ingredient table. They do not include extra mortar for an uneven base, bedding variations, priming slurry, or a separate jointing mortar. The 15 kg jointing compound is one maker’s product example, check that the maker accepts your paving material and joint dimensions before use. Its published coverage is approximate.

Frequently asked questions

How many 600 x 600 mm slabs do I need for 20 m²?

With 10 mm joints and no waste allowance, the calculator estimates 54 slabs. Add an allowance for cuts and breakages to suit the patio layout.

How much MOT Type 1 goes under a patio?

Enter your compacted depth. For the 20 m² worked example at 100 mm, the named merchant's approximate product coverage gives 4 850 kg bulk bags. Actual coverage depends on the supplied product and compaction.

How much sand and cement do I need for a 30 m² patio?

Multiply the patio area by the mortar-bed depth to get cubic metres, then use the sourced 1 : 4 bedding table: 8 x 25 kg cement bags and 1,000 kg of sharp sand per cubic metre. Enter the area and bed depth above to calculate the whole packs.

What density is used for MOT Type 1?

This estimate does not apply a universal density. It uses one merchant’s approximate product coverage at a stated depth to estimate its 850 kg bulk bags, then reports the mass of the whole bags. The merchant’s separate approx. 2 t/m³ density figure conflicts with its own coverage and bag weight.

How much jointing compound do I need?

For this FPM 15 kg example, a 600 x 600 layout with 10 x 25 mm joints covers about 10 m² per tub, so 20 m² needs 2 tubs before extra waste. Check the maker’s product compatibility and coverage for your actual slabs.

Sources

Specs as of:

Embed this calculator

Add this calculator to your website. Copy the HTML into your page to include the calculator, its method and sources.

Visitors can scroll inside the frame to read the full page.

Copy and paste this code into your page’s HTML.

Keep DIYSums handy

Open your browser’s menu and choose Add to Home Screen or Install app.

This lightweight app needs an internet connection. Your calculator inputs stay on your device.

Share calculator